METROPOLITAN PARK APARTMENTS

Owner: Confidential
Architect: Olympic Associates
Start Date: September 2006

 

Extensive decay accelerated by exposure to extreme weather conditions required recladding of the entire apartment building. Charter enclosed the entire 10-story structure in scaffolding to allow access and protect the complex during construction.

Crews replaced all windows, doors, rails and siding; and also installed new Hardiplank and metal corrugated siding with properly integrated flashings and penetration wraps.  Additionally, the west end of the building was re-roofed.

Although repairs in some areas required significant access to the units' interiors, Charter was able to allow the tenants to remain by framing up temporary walls and installing extensive interior protection.

 