Ashford Park

Type: 
Construction Defect Repair
Region: 
Washington
Completion Date: 
05/2004
Architect: 
Olympic Associates
Owner: 
Ashford Park Homeowners Association

Charter beat a fast-paced, 8-month construction schedule to bring this 101-unit condominium recladding project to completion under a tight budget.

Crews demolished the existing siding on Ashford Park’s 33 buildings, removed extensive decay and added new vinyl siding. The compressed schedule required intense collaboration between Charter and the homeowners, who remained in the condos through the duration of the repairs. Charter carefully coordinated its crews and subcontractors during the large project, at times working on six buildings at once.

Crews battled extreme winter weather conditions during construction, encountering snow, hail and freezing temperatures that stopped work for two weeks. Charter reinforced its team, added hours and brought the project to completion as scheduled.